Build with El Biker

Riviera Maya · Municipality of Tulum

Building in Tulum Country Club

We know this development: its blocks, its internal building code, the Comité Técnico, the suppliers who work there and the building methods that hold up in this climate. Before designing your house, the first thing is to know what your lot allows.

Calculate what I can build

The first thing to understand

Here the COS and the CUS belong to your lot, not to the development. The internal building code states that the COS, the CUS and the front, side and rear setbacks of every Unidad Privativa are set out in its public deed and in the attached plan. There is no single figure for the whole of Tulum Country Club: there is yours.

That is why the configurator asks you for those figures if you have them at hand. If you do not, we still show you everything that can be calculated, and we help you read them once you get your deed.

What the building code says

Extracts from the development's internal building code, with the article each one comes from. These are the rules that change a project the most.

4.1.1

The house has to sit inside the EDUC

Every Unidad Privativa has an EDUC defined and marked on the plan attached to its deed. The house must sit inside the EDUC, and the footprint must not exceed the area resulting from applying the COS. Designs that do not comply with the EDUC, the COS and the CUS will not be approved.

4.2.1

The maximum height depends on your block

The maximum height of buildings is specified in the table of restrictions and depends on the block and the land use, measured from the natural or modified ground level to the highest point of the building. For condominiums the maximum height is 16 metres.

4.1.1

The COS and the CUS belong to your lot, not to the development

The COS and the CUS of each Unidad Privativa are set out in its public deed of ownership. The front, side and rear setbacks are described in that same deed and on the lot plan.

4.1.1 A · 4.2.9

The pool and the palapa: what the code says and how it is built today

The area of structures such as swimming pools, plant rooms, palapas, kiosks or caretakers' rooms is included within the COS and CUS area, and has to sit inside the EDUC.

4.2.1

The number of storeys depends on your lot key

The 2014 internal building code set two storeys for houses. The 2024 and 2025 lot sheets authorise up to three storeys on the newer keys, with a maximum height of 10.50 m. The figure that applies is the one on the land-use key of your lot, which appears on your lot sheet. On Unidades Privativas with a steep slope an extra storey may be authorised provided the façade planes, windows and openings do not show it, with the approval of the Comité Técnico.

4.1.1 A.3

Nothing built in the rear setback

No swimming pools, walls, footpaths or golf-cart ramps may be built in the rear setback. The construction of palapas, kiosks, covered terraces, carports and plant rooms in that setback is strictly prohibited. The whole area is to be native jungle.

4.1.1 A.1

The front setback is native jungle

Only the strictly necessary footpaths and vehicle ramps may be built in the front setback. The rest is to be native jungle, treated according to the General Landscape Architecture Plan.

4.2.6

Walls white on at most 75 %, stone on at least 25 %

The colour of the exterior walls must be white on at most 75 % and combined with stone on at least 25 %, subject to the approval of the Comité Técnico. Exterior materials have to be approved with physical samples.

4.2.6

Prohibited exterior materials

The external application of reflective metal elements and cladding, vinyl, reflective surfaces, asbestos and PVC is not permitted.

4.2.6

Only clear, green-tinted or frosted glass

Mirrored glass in any shade is not permitted, nor is polarised or smoked glass. Only clear or transparent glass, green tints and frosted or acid-etched glass are allowed.

4.2.2

No domes

Playing with wall and roof planes may be used to give movement and visual interest; the use of domes is prohibited.

4.2.5

Roofs in natural colours

Roofs may not be painted in bright colours or in any colour other than the natural colours of the materials. Finishes and materials must be authorised in advance by the Comité Técnico.

6.5

Every project goes through the Comité Técnico

Before any conceptual planning, the Comité Técnico must be consulted to verify the specific location of the EDUC. The project goes through a preliminary meeting, an initial presentation, an evaluation, a final presentation and final approval before the building licence.

6.1

A 200,000-peso bond, index-linked

Owners and their builders must post a bond to guarantee compliance with the building code, for $200,000.00 MXN, updated at the start of the works at a rate equal to the INPC published by the Bank of Mexico.

6.1

The works cannot stand unfinished for more than 18 months

If the construction departs from the approved project or is left unfinished for 18 months from the start date, the bond will be called in to correct the departures and finish the works.

6.6

Requirements before starting the works

No works may begin without the final approval of the Comité Técnico, the municipal building licence, and the corresponding bond and insurance. Every site must be hoarded from the outset with attractive elements that block the view from outside; the use of construction timber for the hoarding is prohibited.

Anexo C 3.14

Working hours on site

Monday to Friday from 7:00 to 18:00. Saturdays from 7:00 to 14:00. Sundays and the public holidays of the Federal Labour Law are not working days.

4.1.1 A.5

Conservation of the native jungle

The COS area is delimited within the Unidad Privativa and clearing is permitted only inside it. The rest of the lot is kept as native jungle in accordance with the General Landscape Architecture Plan and the authorised plant palette.

2.2

The Tulum municipal building code also applies

Being located in the Municipality of Tulum, the Building and Urban Services Regulations of the Municipality of Tulum must be observed and complied with for everything the condominium's internal building code does not cover.

Building code

Perimeter wall

The perimeter wall is optional and may not exceed 1.20 m in height.

Blocks in the development

Residential

Manzana 1 Manzana 2 Tao · Manzana 3 Manzana 4 Terrazas · Manzana 5 Manzana 6 Green 3 · Manzana 7 Las Flores · Manzana 8 Quetzal · Manzana 9 Manzana 10 Manzana 13 Hélices II · Manzana 16 Las Olas · Manzana 17 Manzana 18 Downtown · Manzana 19 Villas Caribe · Manzana 21 Lagos · Manzana 23 Bosques de la Herradura · Manzana 24 Manzana 25 Tortugas · Manzana 26 Manzana 39 Manzana 40 Manzana 41 Manzana 43 Park Village · Manzana 49 Manzana 52 Sunset · Manzana 53 Manzana 54 Park Garden · Manzana 55

Mixed use

Manzana 11 Manzana 12 La Herradura · Manzana 15 Manzana 22 Manzana 27 Manzana 45 Manzana 46 Manzana 47

Each block can have a different maximum height under the development's table of restrictions, and each lot its own COS, CUS and setbacks.

What each number means

COS is the percentage of the lot you may cover with the ground floor of your house. A COS of 0.35 on 400 m² allows a 140 m² footprint.

CUS is the total built area you may add up across all storeys.

EDUC is the polygon drawn on your lot plan within which the house has to sit. It is not the same as the COS: the COS tells you how many square metres, the EDUC tells you where.

The perimeter setbacks are the metres you must leave clear against each boundary, and in this development that strip is kept as native jungle. In practice they are usually what limits a project the most.

One detail that surprises many people: here the pool, the palapa, the kiosk and the plant room count towards the COS and the CUS. They are not extra area: they take square metres away from the house. The configurator calculates it that way from the start.

Start my project

Sources

The information on this page is a summary of the development's internal regulations. For legal purposes the original document and whatever the Comité Técnico resolves are what govern.

Message me on WhatsApp